What the Port Orange permit desk wants before the first footing
The city runs building permits through its SmartGov portal. The Community Development Building Division says an application "will not be processed" until every checklist item is uploaded. If the job changes the outside dimensions of a house, and that means additions, garages and new homes, the city wants a certified survey and a site development plan drawn at 1 inch to 20 feet for lots up to an acre.
The plan has to show every existing and proposed driveway, sidewalk and patio, with its material, size and distance to the lot lines. The grading plan then adds finish elevations for floors, patios, driveways, the street crown and the lot corners. Those elevations matter most for a foundation. Your floor height gets measured against the road and the water.
Send us the survey and plans before you file and we'll mark up whatever's missing. Countywide rules live in our Volusia County concrete permit guide, and the rest of what we do in the city is on the local concrete contractors page.